Configure Quality Project Management > Customize RYG rating behavior
Customize the RYG rating behavior in Quality Project Management
The red, yellow, green (RYG) ratings are used at the program, project, subproject, event, checklist, and question level to indicate the status of the various criteria. You can customize the RYG rating behavior by using BMIDE business object constants.
Procedure
Open BMIDE with the apm0apqpprogrammgt solution template.
Search for the Psi0ChecklistQuestion business object.
Click the Business Objects Constant tab and edit the Apm0RYGAssessmentRuleGreen business object constant. The default value is Psi0IsMandatory:true,psi0Answer.Yes. This value means that if the mandatory question is answered, the system automatically assigns the green color to the checklist business object based on default rules.You can remove the default value, for example, if you do not want the rating behavior to be based on mandatory questions.
Edit the Apm0RYGAssessmentRuleRed business object constant. The default value is Psi0IsMandatory:true,psi0Answer.No. This value means that if the mandatory question is not answered, the system automatically assigns the red color to the checklist business object based on default rules.You can remove the default value, for example, if you do not want the rating behavior to be based on mandatory questions.
Select the Apm0RYGThresholdOfYellowGreen business object constant, click Edit, and change the Value as appropriate. The default value is 1.
Example If you specify the value of this constant as 2, the RYG rating becomes Red if two RYG values of plan level objects such as such as program, event, checklist, or checklist question are red. Similarly, if you specify the value of this constant as 3, the RYG rating becomes Red if three RYG values of plan level objects such as such as program, event, checklist, or checklist question are red.
Caution Do not specify a negative value for this business object constant.
Select the Apm0RYGThresoldOfRedYellow business object constant, click Edit, and change the Value as appropriate. The default value is 1.
Example If you specify the value of this constant as 2, the RYG rating becomes Yellow if two RYG values of plan level objects such as such as program, event, checklist, or checklist question are yellow. Similarly, if you specify the value of this constant as 3, the RYG rating becomes Yellow if three RYG values of plan level objects such as such as program, event, checklist, or checklist question are yellow.
Search for the Psi0Checklist, Prg0AbsPlan, and Prg0AbsEvent business objects and open them in separate tabs to edit them. Click the Business Objects Constant tab and repeat step 2.c and step 2.d.
Create a custom template with the changes in BMIDE.
Deploy the template with the changes.For more information about deploying templates in BMIDE, see Deploy a template.