QualityKnowledge

Optimize the identified risks

Assign users responsible for the prevention or detection actions

Assign responsible users to prevention and detection actions for failure causes and set due dates for completion.

Procedure

  1. Open the FMEA and click the Risk Analysis and Optimization tab.

  2. Select the quality action in the Failure Actions or Failure Root Cause Actions table.

  3. Choose More Commands > Manage > Assign Responsible User.

  4. In the Assign Responsible User panel, select the required users and click Assign.

  5. To specify the due date, double-click the respective cell in the Due Date column, and select the due date as required.